The Good Fight: The Klamath Dams are Coming Down

By B. ‘Toastie’ Oaster / High Country News

Editor’s note: In lieu of the Letters column that usually runs in this space, we’re bringing you important and gratifying news regarding the removal of four dams on the Klamath River that have long blocked passage upriver for steelhead and salmon.

The Federal Energy Regulatory Commission (FERC) in Washington, D.C., held a final vote in November to decide on the removal of four dams on the lower Klamath River. The vote, which follows the agency’s final environmental impact statement in late August, was unanimous in favor of removal.

After a grueling 20 years of environmental impact statements, scientific studies, negotiations with stakeholders and advocacy from the tribes and their conservationist allies — people who, as Hoopa Valley Tribe Chairman Joe Davis said, “poured their blood, sweat and tears into making this happen” — the vote is the final green light everyone’s been waiting for. With FERC’s laborious approval process now concluded, dam removal can begin, launching what is expected to be the biggest river restoration project in U.S. history.

“The Klamath salmon are coming home,” said Joseph James, the chairman of the Yurok Tribe, in a statement. “The people have earned this victory and with it, we carry on our sacred duty to the fish that have sustained our people since the beginning of time.”

The next legal steps are largely technical. As a result of the vote, FERC is ordering the surrender of the Lower Klamath Project License, which is currently held by energy company PacifiCorp. That license will be transferred to the entities in charge of dam removal: the states of Oregon and California, and the Klamath River Renewal Corporation, a nonprofit created to oversee dam removal that is made up of tribal, state and conservation group representatives.

FERC’s final environmental impact FERC vote by acknowledging that the only practical path to saving the Klamath’s salmon is the removal of the four lowermost dams: COPCO 1, COPCO 2, Iron Gate and JC Boyle Dams. PacifiCorp, their owner, had concluded that these outdated, inefficient hydroelectric dams would be more difficult to update than to remove. The dams don’t provide water for irrigation and are not involved in the conflicts around irrigation water in the upper Klamath Basin. The river’s two uppermost dams, which do provide water for irrigation and which also have fish ladders, will remain in place.


The salmon won’t return overnight. The first step in dam removal is, counterintuitively, to build roads. Removal requires a lot of heavy machinery and infrastructure, so the first year of the process will be dedicated to getting the dam sites ready for demolition and hauling in necessary equipment.

In early 2024, the reservoirs are scheduled to be drawn down between salmon runs, when the sudden release of toxic algal reservoir water will have the least possible impact on river life. In mid-2024, demolition will begin with COPCO 2, the smallest dam, slated as the first to come down. By October 2024, the pathway should be open for the salmon’s return.

Removal of the four lower dams will give endangered salmon and other anadromous fish access to around 400 miles of spawning habitat that’s been locked away since 1918, when the California Oregon Power Company (COPCO, now PacifiCorp) split the basin in half by building COPCO 1 dam. Although on paper FERC is ordering PacifiCorp to surrender the dam license, the energy company has become a willing participant in the push for dam removal.

Read the full story at https://www.hcn.org/articles/indigenous-affairs-dams-theklamath-dams-are-coming-down.